- EMS ÀÏ˾»ú¸£ÀûÉç Bond Progress
- Liz Hatley Elementary School
-
Projected Opend: August 2023
Mascot: Falcons
Colors: Purple and GrayJuly 24, 2023 Update
-
Landscaping continues around all areas of the site. The office area is undergoing final punch list corrections. Main foyer flooring is complete with wall tile receiving grouting.
- Kitchen and serving lines have been completed and final cleaning and are ready for kitchen staff. Stage area is receiving punch item completion.
- Gymnasium school logo painting is near completion. Outside basketball court and sidewalks have been completed.
-
Hatley Move Timeline
•7/13 –LCO (Limited Certificate of Occupancy) to begin delivery and assembly of furniture in the cafeteria, administration, and library areas.
•7/18 –Delivery of custodial supplies and set up of trash cans.
•7/24 –LCO (Limited Certificate of Occupancy) second floor furniture delivery.
•7/25 –TCO (Temporary Certificate of Occupancy) for staff.
•7/26 –Tentative move in date for administration.
•7/27 –Basic Book pallets will be delivered to the campus.
•7/31 –Custodial staff will begin cleaning.
•8/1 –Campus professional development day. A detailed map for parking and entry will be created for the event.
•8/4 –Custodians will begin waxing.
•8/7 –Teachers will move into the building.
June 12, 2023 Update
- Installation of millwork in the admin area is almost complete.
- Ceiling tile and restroom floor tiles completed in areas A and B.
- Library ceiling grid has been installed and panels have been delivered.
- Ceiling grid and floor tile in cafeteria have been installed.
- Duct work and sheetrock installation continue in area D2.
- Connector walk way on the second floor is being prepped for glass installation. Basketball court and mow strip for playground have been poured.
- Brick layers continue installation in area D on the north and west walls.
May 22, 2023 Update
- Brick work is complete in academic wing C and is progressing in academic area D.
- Driveway approaches around the site are being poured.
- Administrative area continues with the installation of doors and library glass.
- Tile work is completed in the administrative area and continues in the hallway between the gymnasium and cafeteria. Lighting fixtures have been installed in areas A and B.
- Flooring protection is in place in the kitchen as equipment has been installed.
- These photos show the different progression from the top and bottom levels in area C and D.
April 24, 2023 Update
- Landscaping continues on the west and south side of the campus.
- Brick and rock installation are progressing on the administration and library areas.
- Sheetrock, tape and bedding and painting continue in the administrative area.
- Brick work is near completion in the gym area. Installation of an electrical transformer has been completed.
March 27, 2023 Update
- Main entrance and library continue with rough-in mechanical work. The roof on the library has been completed.
- Brick on the exterior of the gymnasium has begun. CMU block is complete in the gym and mezzanine areas.
- Storefront frames have been installed in the cafeteria. Landscaping, trenching and main lines are being installed.
- Sheetrock has started in the office area. Interior metal studs are progressing in the academic areas.
- Work continues on the mezzanine platform on the two academic wings.
February 27, 2023 Update
- Work continues on the main hallway and library. Installation of metal studs and HVAC duct work is in progress.
- Work continues on the second floor decking.
- Both bottom photos are of the cafeteria, focusing on the ceiling and stage construction.
November 14, 2022 Update
- Work on the ICF in the cafeteria continues. A grease trap has been installed.
- Piers and storm water continue to progress.
October 24, 2022 Update
- Storm water and GEO wells are in progress.
- Rough-in plumbing continues in the kitchen in preparation for the slab pour.
September 19, 2022 Update
- Overview of the site showing the main gymnasium and cafeteria areas.
- Steel installation for the grade beams is in progress.
-
-
July 24, 2023
-
June 12, 2023
-
May 22, 2023
-
April 24, 2023
-
March 27, 2023
-
February 2023
-
November 14, 2022
-
October 24, 2022
-
September 19, 2022