Marine Creek Middle School
In a presentation to the Board of Education on January 16, 2018, Chief Operations Officer Clete Welch provided the following updates about Marine Creek Middle School to the Board:
- The grade beam steel has been delivered
- Area D piers are complete
- Area A piers are being layered out
- Moisture conditions continued around the football area
- Manholes are being poured on the east close to Marine Creek Parkway
- Area D at 75% beams completed
- Plumbers mobilizing – installing sleeves as needed
- Brick and rock mock-ups are on site