- Copper Creek Elementary School
Copper Creek Elementary School
-
The District closed on the property for Copper Creek Elementary School on February 13, 2018.
Projected Opening: August 2020
Mascot: Cowboys
Colors: Cardinal & Old GoldAugust 2020 Update:
- Temporary Certificate of Occupancy has been received for staff and students
July 2020 Update:
- Staff waxing floors
June 2020 Update:
- Building sinage is installed.
- Hat channel being installed to receive acoustical panel.
- Concrete is being prepped for flooring.
- Classrooms are locked and ready for furniture.
- Playground area is being landscaped.
May 2020 Update:
- Main lobby is being completed and finishes are being installed.
- Ceiling clouds are being installed.
- A masonry wall within the tornado scruture is installed. Duct work and lighting are also being installed.
- Gym masonry is progressing.
- Sidewalks are being isntalled between the academic wings.
- They playground system is installed.
April 2020 Update
- The cafeteria serving line is finished.
- The library cerculation desk area is finished.
- Classroom hallways are painted.
- Finished classrooms are carpeted and include cabinets and sinks.
March 2020 Update:
- Installation of tornado shelter
- Front view of school showing the new gym
- Library
- Main hallway entrance
- West view with main student pick-up area
- Sidewalk preparation for playground structure
February 2020 Update:
- Front view of main opening
- Progress of brick and stone
- Administrative area
- Library, ceiling grid, and paint
- Computer lab
- Cafeteria tiling
- Academic areas
- Academic classrooms
January 2020 Update:
- Aerial view overlooking the cafeteria
- Academic area brick work
- Finishing up steel frame
- Installing windows on 2nd level
- Wall framing in administrative area
- Academic area 2 sheet rock complete in hallway
- Wall framing on 2nd floor
- Wainscoting complete in hallway between cafeteria and gym
- Library windows installed
- Kitchen wall tile complete. Work continues on the flooring
- Bus canopy columns installed
- Gym walls have been delayed
December 2019 Update:
- Site work continues.
- The walls for the gymnasium/storm shelter are being constructed off site.
- Ceiling work, tiling, tape and bedding and painting is in progress in the kitchen and serving line.
- Kitchen equipment is being installed.
- Framing and sheetrock work is occurring in the library.
November 2019 Update:
- Masonry and windows near completion in the cafeteria area.
- Scaffolding is on site to brick the building.
- Masonry, windows and decking are underway in the academic wing.
- Prepping for window installation is underway in a couple of areas.
August 2019 Update:
- All the approaches have been poured.
- The cafeteria and kitchen with ICF forms in place.
- Classroom wings have the beginning of placement of ICF forms.
- Beams have been poured in the hallway between the kitchen and gym.
- Area between the blue fence and the road is the developers land that is dedicated for park land. The greenbelt area also has a walk/biking path.
July 2019 Update:
- Structural slab in cafeteria ready to pour.
- Grading process starting in Area 1.
- ICF blocking on-site and will begin going vertical in the cafeteria.
- Waiting on rebar in Area 2.
- North entrance being poured.
May 2019 Update:
- Contractors are working to minimize traffic through the neighborhood’s amenity center area.
- Pier drilling, utility installation and geothermal drilling is underway.
February 2019 Update:
- Pogue Construction was named as the general contractor for the project. TNP is working with the developer for electrical services and the notice to proceed is March 1, 2019.
-
August 2020 Construction Photos
-
July 2020 Construction Photos
Pictured below: A district staff member waxes the floors. Cafeteria graphics have been installed. The gym floor is complete. The conference room is ready for use.
-
June 2020 Construction Photos
Pictured above from left, concrete is being prepped for flooring. The Hat channel is being installed to recieve acoustical panel.
Pictured above from left, the playground area will be lanscaped. Classrooms are ready for furniture.
Pictured above, signage has been installed.
-
May 2020 Construction Photos
Pictured above from left, ceiling clouds are being installed. Duct work and lighting are being installed in the tornado structure.
Pictured above from left, work is progressing at Copper Creek Elementary School and will open on time in August 2020. Masonry on the gym walls are progressing.
Pictured above from left, the playground structure is installed. Sidewalks are progressing between the academic wings.
-
April 2020 Construction Photos
Pictured above from left, hallways are painted and construction continues on the building. Pictured below, the library circulation desk is complete.
-
March 2020 Construction Photos
-
February 2020 Construction Photos
-
January 2020 Construction Photos
-
December 2019 Construction Photos
-
November 2017 Construction Photos
-
October 2019 Construction Photos
-
September 2019 Construction Photos
-
August 2019 Construction Photos
-
July 2019 Construction Photos
-
May 2019 Construction Photos