• District New Construction Progress

    In a presentation to the Board of Education on March 30, 2020, Chief Operations Officer Clete Welch shared updates about the following projects:

     Copper Creek ES

    • Installation of tornado shelter
    • Front view of school showing the new gym
    • Library
    • Main hallway entrance
    • West view with main student pick-up area
    • Sidewalk preparation for playground structure

     Highland MS

    • Turf field installation 

     Boswell HS

    • Ag building with grade beams installed

     Progress Update of Other Projects

    • Multiple Security Projects – The district will continue to define the scope.
    • Central Office – Continue design meetings. Projected construction will begin in October 2020.
    • Eagle Mountain HS – The district met with VLK to define design timeline. Construction sign installed.