• District New Construction Progress

    In a presentation to the Board of Education on January 21, 2020, Chief Operations Officer Clete Welch shared updates about the following projects:

     Copper Creek ES

    • Aerial view overlooking the cafeteria
    • Academic area brick work
    • Finishing up steel frame
    • Installing windows on 2nd level
    • Wall framing in administrative area
    • Academic area 2 sheet rock complete in hallway
    • Wall framing on 2nd floor
    • Wainscoting complete in hallway between cafeteria and gym
    • Library windows installed
    • Kitchen wall tile complete. Work continues on the flooring
    • Bus canopy columns installed
    • Gym walls have been delayed

     Boswell HS

    • Excavation and pad work at the new Kenneth K. Reed Agricultural Science Building
    • New pathway for students to access the Tim & Vicki Dance Cheer Facility
    • The new outfield baseball/softball fencing is complete

     Progress Update of Other Projects

    • Multiple Security Projects – The district will continue to define the scope
    • Turf Projects – The auxiliary fields at Chisholm Trail HS, Saginaw HS, Prairie Vista MS, Highland MS, Creekview MS, and Ed Willkie MS. The Wayside MS field location is being evaluated. Turf projects will be presented in February 2020. Construction will begin immediately
    • Tennis Court Resurfacing – Saginaw HS, Prairie Vista MS, and Ed Willkie MS
    • Tennis Wind Slats – Saginaw HS, Prairie Vista MS, Ed Willkie MS, and Chisholm Trail HS
    • Track Resurfacing – Chisholm Trail HS, Boswell HS, Saginaw HS, Highland MS, and Creekview MS
    • Carpet and VCT Replacement – Specifications are being developed for carpet and VCT replacement at Saginaw HS, Prairie Vista MS, Comanche
    • Springs ES, Chisholm Ridge ES, and Greenfield ES
    • Central Office – Continue design meetings
    • Projected construction will begin in October 2020
    • Eagle Mountain HS – The next step is to establish a timeline with VLK and a kick-off meeting